TL Monitor
Corridor Intelligence
Select project
Data as on13-Sep-26
Transmission line tracker
400 kV · 81 km · 400kV Z2 – Lakadia · 232 locations · data as on 13-Sep-26
  • Overall progressRoW secured 141/232 (61%) · foundations 98 (42%) plus 15 piles · erection 62 (27%) · stringing 0 (0%)
  • Movement since the last update3 locations changed over 10-Sep-26 → 13-Sep-26 (3 days): RoW 0 · foundation 0 · foundation WIP 0 · erection 0
  • Critical constraintsWaterlogging at 16 locations (foundation at 16) · MRC formation pending at 88
  • Front and forecast41 locations have RoW but no foundation started — the available working front. Foundation +84 d late · Erection +113 d late · Stringing +221 d late
1. Project information
route, locations, land and coverage
Route Length
80.7 km
Pkg-1 39.5 kmPkg-2 40.9 km
Total Locations
232
Pkg-1 108Pkg-2 124
Land Ownership
141 / 232 private · 61%
Govt.91 · 39%Pvt.141 · 61%
Wildlife Sanctuary
40 locs
All 40 RoW secured
Villages Enroute
15
+ RIL / creek stretch · 29 locs
1,010 private land owners
2. Progress as on 13 September 2026
counted from the location register
RoW Secured
141 / 232 · 61%
91 notice issued3 admin support
Foundations Completed
98 / 232 · 42%
2 WIP15 pile done
Front Available
41 / 232 · 18%
RoW secured 141 − foundation done 98 − foundation WIP 2incl. 15 pile front
Towers receipt at site
206 / 232 · 89%
received at site
Tower Erection
62 / 232 · 27%
Tower Erection Front Available
36 locations
foundation complete 98 − erected 62 − erection WIP 0
Stringing
0 locations
Not commenced
Progress as on 13-Sep-26 movement measured over 10-Sep-26 → 13-Sep-26 · 3 days
RoW secured
141/ 232
61%0
Foundation completed
98/ 232
42%0
Foundation WIP
2/ 232
1%0
Pile completed
15/ 232
6%0
Tower erection
62/ 232
27%0
Stringing
0/ 232
0%0
Figures are computed from the location register in the loaded tracker, not entered separately. Nothing moved in this window.
Progress for the weeklive week Sep-26 W2 · 8–14 Sep · 6 of 7 days elapsed at 13 Sep
RoW secured
-1
in Sep-26 W2 · 8–14 Sep
142 → 141
-0.17 locations/day
0 Aug-26 W3
0 Aug-26 W4
+2 Sep-26 W1
-1 Sep-26 W2
Foundation completed
+1
in Sep-26 W2 · 8–14 Sep
97 → 98
0.17 locations/day
+1 Aug-26 W3
+3 Aug-26 W4
+3 Sep-26 W1
+1 Sep-26 W2
Erection completed
+1
in Sep-26 W2 · 8–14 Sep
61 → 62
0.17 locations/day
+6 Aug-26 W3
+7 Aug-26 W4
+1 Sep-26 W1
+1 Sep-26 W2
A week runs 7 days from the 1st of the month (W1 1–7, W2 8–14, W3 15–21, W4 22 to month end). Earlier weeks are declared actuals — Weekly actuals advised by the planning team. Sep-26 W2 is live: it is counted from the register against the position at the start of the week, so it moves every time a newer tracker is uploaded, and is frozen automatically once the week closes. A negative bar is a regression — a location that moved backwards in the tracker.
3. Front available · sequential workflow
clear and constrained next-activity fronts
RoW secured → foundation can start
41available
20 clear 21 constrained
Foundation done → erection can start
36available
36 clear 0 constrained
Erection done → stringing can start
62available
62 clear 0 constrained
4. Tower material delivery
scope, despatch and receipt against erection demand
Tower scope
232
 
Ordered
232
 
MFC issued
232
 
Received at site
206
89% of scope
Balance delivery
26
11% pending
PackageScopeOrdered MFC issuedReceivedBalanceForecast closeoutErection demand now
Pkg-1
M/s JSL
108108108 92
16 20-Aug-2613
Pkg-2
M/s TLL
124124124 114
10 30-Aug-2623
Source: Weekly Progress Update #044 dated 14-Aug-26 — shown as reported. Packages without a reported delivery position show not reported rather than a zero.
5. Key dates for transmission evacuation
as advised by the project management team
VoltageEvacuation capacityTargetForecastVariance
400 kV 0.6 GW 30-Sep-26 30-Nov-26 Delay 61 d
400 kV 2 GW 30-Apr-27 15-Apr-27 Ahead 15 d
6. Critical issues
crossing approvals, severity and schedule delay
Crossing Approvals
7 / 24 approval received
2 high risk
Critical Issues
19 critical
20 high5 medium
Delay Index
+221 days
Foundation +84 dErection +113 dStringing +221 d
9. Detailed progress update
RoW and construction status · 232 locations · data as on 13-Sep-26
Status / metricTotalGovernmentPrivateRILPkg-1Pkg-2
Pkg-1Pkg-2TotalPkg-1Pkg-2TotalJSL
Total locations232306191536311625108124
(A) RoW secured14130619191625256477
(B) Foundation completed982058785152002573
(C) Pile completed1500000015150
(D) Foundation WIP2101011011
(E) Front available = A − B − D41931240425383
(F) Tower erection completed621239510111101250
(G) Stringing completed0000000000
Notice issued / petition filed9100044479104447
Administrative support required0000000000
Wildlife / forest / ESZ0000000000
Every figure is counted from the location register as loaded (232 locations, data as on 13-Sep-26). A land column splits by package only where more than one package works that land type; RIL land is shown as a single entry.
10. Project analytics
critical issues and forecast performance
Top Critical Issues
CriticalRoWMRC formation pending and holding up RoW clearance
88 locations are affected by pending MRC formation / landowner agreement.
Expedite MRC formation and resolve landowner issues to release work fronts · CAD
88locations
10.07 km
HighExecutionWaterlogging is holding up available work fronts
16 locations are temporarily on hold due to waterlogged site conditions.
Resume works immediately after sites become suitable and mobilise required resources · EPC
16locations
3.61 km
Forecast vs Target
Productivity basis assumed
Forecast basis current productivity
Foundation · 98 / 232
+84 d slip
Target
30 Aug
Forecast
21 Nov 26
Req. rate
134/d
Gangs
9
Needs 14.89 per gang per day vs 0.22 assumed — 610 gangs required at that rate
Forecast basis 134 remaining ÷ (0.22 per gang/day × 9 gangs = 1.98 per day) = 68 working days productivity is the assumed rate; gangs are those currently deployed
Erection · 62 / 232
+113 d slip
Target
15 Sept
Forecast
05 Jan 27
Req. rate
170/d
Gangs
5
Needs 34.00 per gang per day vs 0.3 assumed — 567 gangs required at that rate
Forecast basis 170 remaining ÷ (0.3 per gang/day × 5 gangs = 1.50 per day) = 114 working days productivity is the assumed rate; gangs are those currently deployed
Stringing · 0 / 81 km
+221 d slip
Target
25 Sept
Forecast
03 May 27
Req. rate
8.1/d
Gangs
1
Needs 8.10 per gang per day vs 0.35 assumed — 24 gangs required at that rate
Forecast basis 81.0 remaining ÷ (0.35 per gang/day × 1 gang = 0.35 per day) = 232 working days productivity is the assumed rate; gangs are those currently deployed
11. Village-wise and contractor-wise progress
village sequence and package performance
Village-wise Progress Heatmap
left→right = route sequence
RIL Parcel 25
Creek 4
Mauvana 36
Bela 2
Vrajvani 14
Gedi 8
Fatehgarh 2
Gedi 22
Selari 6
Umaiya 22
Pragpar 6
Tindalva 7
Dabhunda 8
Sai 18
Khirai 8
Badargadh 9
Govindpar 10
Shivlakha 25
ConstructionErection completedFoundation completedPile completedFoundation WIP
RoWRoW securedNotice issued / MRCAdmin supportPending / not started
LandGovernmentPrivate
Each block represents one tower/location. Read left to right in route sequence. Construction progress takes priority over the underlying RoW status.
Package Scorecard
Pkg-1 · M/s JSL Kutch Z2 – AP18
39.5 km · 108 locations
RoW secured59%
64/108
Foundation completed23%
25/108
Foundation WIP1%
1/108
Tower erected11%
12/108
Stringing0%
0/108
Pkg-2 · M/s TLL AP18 – ISTS Lakadia
40.9 km · 124 locations
RoW secured62%
77/124
Foundation completed59%
73/124
Foundation WIP1%
1/124
Tower erected40%
50/124
Stringing0%
0/124
Route Corridor
232 locations · 80.68 km · 20 crossings
RIL Parcel · 25Mauvana · 36VrajvaniGediGedi · 22Sel…Umaiya · 22Prag…Tinda…Sai · 18Khir…Badar…Govindp…ShivlakhaWILDLIFE SANCTUARY / ESZSANCTUARYVILLAGECROSSINGSLANDRoWFoundationTower ErectionStringingTesting / Comm.🔌🔌🔌🔌🛢️🛣️01020304050607080kmVILLAGESANCTUARYCROSSINGSLANDRoWFoundationTower ErectionStringingTesting / Comm.
1.0×scroll/pinch = zoom · one-finger drag = pan · click node = details
RoW SecuredNotice issued / MRC*RoW with Admin support
Construction Foundation donePile doneWIPErection doneStringing doneT&C doneNot started
Tower Suspension Tension Forest stretch
Land G Govt.P Pvt.R RIL
Crossings 🚆 Railway crossing🛣️ NH / SH crossing🌊 River / Canal🛢️ Pipeline crossing⚡ 765 / 400 kV line🔌 220 / 132 / 66 kV line📡 PTCC / Telecom⚠️ Other crossing
GIS Route Map
232 of 232 plotted — 232 surveyed, 0 estimated
🔌
🔌
🔌
🔌
🔌
🔌
🛢️
🛢️
🛢️
🛣️
🛣️
Kutch Z2 Gantry
400kV Lakadia Gantry
Leaflet Esri World Imagery
LAND OWNERSHIP
Govt. 91Pvt. 116RIL 25ErectedPending
surveyed position estimated position
Transmission line tracker
1. Project information
route, locations, land and coverage
2. Progress at a Glance
A) Key dates
B) Construction progress
3. Weekly trend: last 4 weeks
Total Crossings
24
5 categories
Approvals Pending
17 / 24
2 high risk
Cleared
7
29% of crossings
Authorities
12
GETCO · PGCIL · ADANI · NHAI · HPCL…
Sanctuary Locations
0 locs
0 of 0 still open
Hindrance Locations
5
encroachment · police support
Statutory Crossing Approval Pipeline
🔌220 / 132 / 66 kV line · 9
22/4 - 22/5
TLL · 22/4–22/5 · 53.35 km
66KV S/C H-Frame Rapar - Pragpar TL · GETCO
Pending with C.E & RO Vadodara
Medium
11/14 stages
AP 30 - AP 32
TLL · 30/0–32/0 · 61.78 km
500kv Mundra - Mahendragadh · ADANI
Pending with Adani Engg.
Medium
5/14 stages
AP 36 - AP 37
TLL · 36/0–37/0 · 66.93 km
66kv S/C Khirai - Sai · GETCO
Pending with C.E & RO Vadodara
Medium
11/14 stages
AP 36 - AP 37
TLL · 36/0–37/0 · 66.93 km
66kv S/C Shivlakha - Khirai · GETCO
Pending with C.E & RO Vadodara
Medium
11/14 stages
37/2 - AP 39
TLL · 37/2–39/0 · 67.99 km
66KV Shivlakha - Rapar · GETCO
Pending with C.E & RO Vadodara
Medium
11/14 stages
AP 40 - AP 41
TLL · 40/0–41/0 · 70.51 km
66KV S/C Chitroad - Rapar · GETCO
Pending with C.E & RO Vadodara
Medium
11/14 stages
TLL + JSL · not located
· AAI
Cleared / NOC in place
Low
5/11 stages
TLL + JSL · not located
· AAI
Cleared / NOC in place
Low
5/11 stages
TLL + JSL · not located
· CEA
Cleared / NOC in place
Low
0/8 stages
765 / 400 kV line · 9
AP 28 - AP 29
TLL · 28/0–29/0 · 61.60 km
765kv Bhuj - Banashkatha TL · PGCIL
Pending with Engg. team. Gurgaon
Medium
8/14 stages
AP 44 - AP 45
TLL · 44/0–45/0 · 72.05 km
400KV D/C Mundra - Zerda (U/c) · GETCO
Pending with C.E & RO Vadodara
Medium
11/14 stages
AP 44 - AP 45
TLL · 44/0–45/0 · 72.05 km
400 KV Bhachau - Vadavi · PGCIL
Cleared / NOC in place
Low
9/14 stages
AP 44 - AP 45
TLL · 44/0–45/0 · 72.05 km
400 KV Versana - Charanka · GETCO
Pending with C.E & RO Vadodara
Medium
11/14 stages
AP 45 - AP 46
TLL · 45/0–46/0 · 72.28 km
400kv Mundra - Dehgam · ADANI
Cleared / NOC in place
Low
8/14 stages
AP 52 - AP 53
TLL · 52/0–53/0 · 75.27 km
765kV Lakadia - Banaskantha · ADANI
Connected with Mr. Chirag Gandhi (8980802212) for review, Observatio
Medium
5/14 stages
AP 57 - AP 58
TLL · 57/0–58/0 · 77.24 km
765kV Ahmedabad - Lakadia · PESL
Pending with Engg. team. Gurgaon
Medium
8/14 stages
AP 60 - AP 61
TLL · 60/0–61/0 · 77.59 km
765kV Lakadia - Vadodara · STERLITE
Pending with Resonia Engg.
High
2/14 stages
AP70A-AP71
TLL · 70A/0–71/0 · 80.59 km
765 kV D/C KPS-III- Lakadia TL · ADANI
Pending with Adani Engg.
High
3/14 stages
🛢️Pipeline crossing · 3
AP 49 - AP 50
TLL · 49/0–50/0 · 73.95 km
Oil Pipe Line (Mundra-Delhi) HPCL-MDPL · HPCL
Requirement compliance pending with TLL
Medium
7/13 stages
AP 49 - AP 50
TLL · 49/0–50/0 · 73.95 km
Crude Oil Pipe Line (Mundra-Bhatinda) HPCL Mittal Energy Ltd. · HMEL
Cleared / NOC in place
Low
7/13 stages
AP 49 - AP 50
TLL · 49/0–50/0 · 73.95 km
Oil Pipe Line (Rajasthan - Mundra) HPCL Rajasthan Refinary Ltd · HRRL
Demand note revision pending with HRRL
Medium
9/13 stages
🛣️NH / SH crossing · 2
AP8-AP9
JSL · 8/0–9/0 · 14.79 km
NH-754K (AMRITSAR-JAMNAGAR) · NHAI
Pending with S.E. Gandhimnagar
Medium
9/13 stages
AP 36 - AP 37
TLL · 36/0–37/0 · 66.93 km
N.H.-927C Chitrod To Balasar · NHAI
Pending with S.E. Gandhimnagar
Medium
9/13 stages
📡PTCC / Telecom · 1
AP1-AP71
JSL · whole line
PTCC proposal for 400 kV D/C Z2 (Kutch)-Lakadia TL · BSNL DET (Divisional Engineer telegraph) PTCC, Mumbai
Cleared / NOC in place
Low
4/12 stages
Hindrance Register
LocationVillagePkgHindrance typeStatusDetail / action
8/0MauvanaJSL Govt land / encroachment Front Available - Open CastLocation attempted on 23-Jul-26. Mauvana village Sarpanch has stopped the work at site. Under Negotiation with Mamlatdar
9/0MauvanaJSL Govt land / encroachment Front Available - Open CastPit Marking done. Under Negotiation
24A/1DabhundaTLL Govt land / encroachment Encroachment, DILR support requiredPolice support is required - Discussion done with PI Rapar for support
25/0DabhundaTLL Govt land / encroachment SDM/Mamlatdar/Police support requirePolice support is required - Discussion done with PI Rapar for support
25/1DabhundaTLL Govt land / encroachment Encroachment, DILR support requiredPolice support is required - Discussion done with PI Rapar for support
2/0RIL ParcelJSL Access / weather Waterlogging - temporarily on hold
2/1NRIL ParcelJSL Access / weather Waterlogging - temporarily on hold
2A/0RIL ParcelJSL Access / weather Waterlogging - temporarily on hold
2B/0RIL ParcelJSL Access / weather Waterlogging - temporarily on hold
4/0NRIL ParcelJSL Access / weather Waterlogging - temporarily on hold
4/1NRIL ParcelJSL Access / weather Waterlogging - temporarily on hold
4B/0NRIL ParcelJSL Access / weather Waterlogging - temporarily on hold
4C/0NRIL ParcelJSL Access / weather Waterlogging - temporarily on hold
4C/1NRIL ParcelJSL Access / weather Waterlogging - temporarily on hold
4D/0NRIL ParcelJSL Access / weather Waterlogging - temporarily on hold
4E/0NCreekJSL Access / weather Waterlogging - temporarily on hold
5/0NCreekJSL Access / weather Waterlogging - temporarily on hold
5/1NCreekJSL Access / weather Waterlogging - temporarily on hold
6/0NCreekJSL Access / weather Waterlogging - temporarily on hold
6/1MauvanaJSL Access / weather Waterlogging - temporarily on hold
17/0GediJSL Access / weather Waterlogging - temporarily on hold
Critical Issue Engine
31 of 31 issues · 10 critical
CriticalRoWMRC formation pending for 88 private-land locations
Sec.16(1) notices issued; 88 locations (38% of route) await MRC/compensation determination across 11 villages.
Weekly MRC calendar with Mamlatdar; target 25 locations/week · CAD
88locations
10.07 km
CriticalBlocking11 consecutive blocked locations 9/3 → 10/6
Continuous 3.93 km stretch with no clear front – breaks stringing continuity. Villages: Mauvana.
Prioritise this stretch; single-window MRC drive · Project Director
11locations
16.01 km
CriticalBlocking11 consecutive blocked locations 35/2 → 39/5
Continuous 3.59 km stretch with no clear front – breaks stringing continuity. Villages: Badargadh, Khirai.
Prioritise this stretch; single-window MRC drive · Project Director
11locations
66.41 km
CriticalBlocking11 consecutive blocked locations 51/0 → 58/0
Continuous 2.17 km stretch with no clear front – breaks stringing continuity. Villages: Shivlakha.
Prioritise this stretch; single-window MRC drive · Project Director
11locations
75.12 km
CriticalBlocking7 consecutive blocked locations 15/1 → 16/4
Continuous 2.30 km stretch with no clear front – breaks stringing continuity. Villages: Gedi.
Prioritise this stretch; single-window MRC drive · Project Director
7locations
33.31 km
CriticalBlocking7 consecutive blocked locations 22/5 → 23A/1
Continuous 2.77 km stretch with no clear front – breaks stringing continuity. Villages: Pragpar, Tindalva.
Prioritise this stretch; single-window MRC drive · Project Director
7locations
53.53 km
CriticalBlocking6 consecutive blocked locations 6/2 → 6/7
Continuous 1.96 km stretch with no clear front – breaks stringing continuity. Villages: Mauvana.
Prioritise this stretch; single-window MRC drive · Project Director
6locations
10.07 km
CriticalBlocking5 consecutive blocked locations 10/8 → 10/12
Continuous 1.60 km stretch with no clear front – breaks stringing continuity. Villages: Mauvana.
Prioritise this stretch; single-window MRC drive · Project Director
5locations
20.75 km
CriticalCrossing765 / 400 kV line approval pending – STERLITE
765kV Lakadia - Vadodara · Section AP 60 - AP 61 · stuck at: Pending with Resonia Engg.
Pursue with authority; escalate to nodal officer · CAD/EPC
1item
77.59 km
CriticalCrossing765 / 400 kV line approval pending – ADANI
765 kV D/C KPS-III- Lakadia TL · Section AP70A-AP71 · stuck at: Pending with Adani Engg.
Pursue with authority; escalate to nodal officer · CAD/EPC
1item
80.59 km
HighSequence62 towers erected, stringing not commenced
Stringing at 0 of 81 km; 1 stringing gang(s) available. Target 2026-09-25.
Mobilise minimum 4 stringing gangs; release PTCC/crossing clearances first · EPC
62locations
12.76 km
HighSequence36 foundations complete but erection not started
Idle erection front of 36 locations across 9 villages. Only 5 erection gangs deployed.
Mobilise additional erection gangs; sequence by village cluster · EPC
36locations
12.42 km
HighAccessPolice/SDM support required at 3 locations
25/0 (Dabhunda) – Police / SDM / Mamlatdar support required; 25/1 (Dabhunda) – Police / SDM / Mamlatdar support required; 61/0 (Shivlakha) – Police / SDM / Mamlatdar support required
Formal requisition to SDM & DySP; fix joint visit date · CAD
3locations
58.66 km
HighCrossing220 / 132 / 66 kV line approval pending – GETCO
66KV S/C H-Frame Rapar - Pragpar TL · Section 22/4 - 22/5 · stuck at: Pending with C.E & RO Vadodara
Pursue with authority; escalate to nodal officer · CAD/EPC
1item
53.35 km
HighCrossing765 / 400 kV line approval pending – PGCIL
765kv Bhuj - Banashkatha TL · Section AP 28 - AP 29 · stuck at: Pending with Engg. team. Gurgaon
Pursue with authority; escalate to nodal officer · CAD/EPC
1item
61.60 km
HighCrossing220 / 132 / 66 kV line approval pending – ADANI
500kv Mundra - Mahendragadh · Section AP 30 - AP 32 · stuck at: Pending with Adani Engg.
Pursue with authority; escalate to nodal officer · CAD/EPC
1item
61.78 km
HighCrossing220 / 132 / 66 kV line approval pending – GETCO
66kv S/C Khirai - Sai · Section AP 36 - AP 37 · stuck at: Pending with C.E & RO Vadodara
Pursue with authority; escalate to nodal officer · CAD/EPC
1item
66.93 km
HighCrossing220 / 132 / 66 kV line approval pending – GETCO
66kv S/C Shivlakha - Khirai · Section AP 36 - AP 37 · stuck at: Pending with C.E & RO Vadodara
Pursue with authority; escalate to nodal officer · CAD/EPC
1item
66.93 km
HighCrossing220 / 132 / 66 kV line approval pending – GETCO
66KV Shivlakha - Rapar · Section 37/2 - AP 39 · stuck at: Pending with C.E & RO Vadodara
Pursue with authority; escalate to nodal officer · CAD/EPC
1item
67.99 km
HighCrossing220 / 132 / 66 kV line approval pending – GETCO
66KV S/C Chitroad - Rapar · Section AP 40 - AP 41 · stuck at: Pending with C.E & RO Vadodara
Pursue with authority; escalate to nodal officer · CAD/EPC
1item
70.51 km
HighCrossing765 / 400 kV line approval pending – GETCO
400KV D/C Mundra - Zerda (U/c) · Section AP 44 - AP 45 · stuck at: Pending with C.E & RO Vadodara
Pursue with authority; escalate to nodal officer · CAD/EPC
1item
72.05 km
HighCrossing765 / 400 kV line approval pending – GETCO
400 KV Versana - Charanka · Section AP 44 - AP 45 · stuck at: Pending with C.E & RO Vadodara
Pursue with authority; escalate to nodal officer · CAD/EPC
1item
72.05 km
HighCrossing765 / 400 kV line approval pending – ADANI
765kV Lakadia - Banaskantha · Section AP 52 - AP 53 · stuck at: Connected with Mr. Chirag Gandhi (8980802212) for review, Observations received from Adani on 13-04-2026. Pending with TLL for compliance.
Pursue with authority; escalate to nodal officer · CAD/EPC
1item
75.27 km
HighCrossing765 / 400 kV line approval pending – PESL
765kV Ahmedabad - Lakadia · Section AP 57 - AP 58 · stuck at: Pending with Engg. team. Gurgaon
Pursue with authority; escalate to nodal officer · CAD/EPC
1item
77.24 km
HighCrossingPipeline crossing approval pending – HPCL
Oil Pipe Line (Mundra-Delhi) HPCL-MDPL · Section AP 49 - AP 50 · stuck at: Requirement compliance pending with TLL
Pursue with authority; escalate to nodal officer · CAD/EPC
1item
73.95 km
HighCrossingPipeline crossing approval pending – HRRL
Oil Pipe Line (Rajasthan - Mundra) HPCL Rajasthan Refinary Ltd. · Section AP 49 - AP 50 · stuck at: Demand note revision pending with HRRL
Pursue with authority; escalate to nodal officer · CAD/EPC
1item
73.95 km
HighCrossingNH / SH crossing approval pending – NHAI
NH-754K (AMRITSAR-JAMNAGAR) · Section AP8-AP9 · stuck at: Pending with S.E. Gandhimnagar
Pursue with authority; escalate to nodal officer · CAD/EPC
1item
14.79 km
HighCrossingNH / SH crossing approval pending – NHAI
N.H.-927C Chitrod To Balasar · Section AP 36 - AP 37 · stuck at: Pending with S.E. Gandhimnagar
Pursue with authority; escalate to nodal officer · CAD/EPC
1item
66.93 km
MediumWeather16 locations on hold – waterlogging
Front available but not workable. Creek, Gedi, Mauvana, RIL Parcel. Monsoon dependency.
Re-sequence gangs to dry stretches; plan dewatering · EPC
16locations
3.61 km
MediumDataChainage is estimated for 19 of 232 locations
Only 213 locations have surveyed span data. Pkg-2 are positioned from the package route lengths in the weekly pictorial rather than measured spans, so individual chainages are indicative.
Issue the survey span schedule per package to replace estimated chainage · Planning / Survey
0locations
41.36 km
MediumDataRecorded span disagrees with the surveyed distance at 6 crossing(s)
AP 44 - AP 45: sheet says 338 m, towers are 166 m apart; AP 44 - AP 45: sheet says 338 m, towers are 166 m apart; AP 44 - AP 45: sheet says 338 m, towers are 166 m apart; AP 49 - AP 50: sheet says 326 m, towers are 599 m apart; AP 49 - AP 50: sheet says 326 m, towers are 599 m apart; AP 49 - AP 50: sheet says 326 m, towers are 599 m apart. Either the "Span (Mtr)" column is the crossing width rather than the tower-to-tower span, or it predates the current alignment.
Confirm which figure the crossing applications were made against · CAD / Survey
0locations
72.05 km
S-Curve — Planned vs Actual vs Forecast
Productivity & Forecast Simulator
Foundation
balance 134 nos
Gangs 30
Duration
20 d
Completion
04 Oct 26
vs Target
+36 d
Erection
balance 170 nos
Gangs 30
Duration
19 d
Completion
03 Oct 26
vs Target
+19 d
Stringing
balance 81 km
Gangs 24
Duration
10 d
Completion
24 Sept 26
vs Target
0 d
Productivity per gang per day — foundation 0.22, erection 0.3, stringing 0.35 km — Forecast basis current productivity Drag to model mobilisation scenarios.
Bottleneck Analysis — Blocking Clusters
Continuous stretches with no clear front — these break stringing continuity and idle the erection gangs.
1
9/3 → 10/6 · 11 locations
Continuous 3.93 km stretch with no clear front – breaks stringing continuity. Villages:
16.01 km
2
35/2 → 39/5 · 11 locations
Continuous 3.59 km stretch with no clear front – breaks stringing continuity. Villages:
66.41 km
3
51/0 → 58/0 · 11 locations
Continuous 2.17 km stretch with no clear front – breaks stringing continuity. Villages:
75.12 km
4
15/1 → 16/4 · 7 locations
Continuous 2.30 km stretch with no clear front – breaks stringing continuity. Villages:
33.31 km
5
22/5 → 23A/1 · 7 locations
Continuous 2.77 km stretch with no clear front – breaks stringing continuity. Villages:
53.53 km
6
6/2 → 6/7 · 6 locations
Continuous 1.96 km stretch with no clear front – breaks stringing continuity. Villages:
10.07 km
7
10/8 → 10/12 · 5 locations
Continuous 1.60 km stretch with no clear front – breaks stringing continuity. Villages:
20.75 km
Contractor Performance
1
Pkg-2 · M/s TLL AP18 – ISTS Lakadia · 124 locs
Fdn 59% Erection 40% RoW 62%
52
2
Pkg-1 · M/s JSL Kutch Z2 – AP18 · 108 locs
Fdn 23% Erection 11% RoW 59%
26
Composite score = 40% foundation + 40% erection + 20% RoW completion, within each package's own scope.
Week-on-week progress — last 4 weeks
RoW · Foundation · Erection · Stringing
Weekly Look-Ahead — Ready Fronts by Village
locations with RoW secured & next activity pending
Foundation-ready fronts · 43
RoW secured, foundation not yet complete — deploy foundation gangs here first.
RIL Parcel 1/0, 1/1, 1/2, 1/3 +21 25
Creek 4E/0N, 5/0N, 5/1N, 6/0N 4
Mauvana 6/1, 8/0, 9/0, 10/13 4
Gedi 13/4, 16/5, 17/0 3
Fatehgarh 14/5, 15/0 2
Dabhunda 25/0, 25/1 2
Vrajvani 11/0 1
Erection-ready fronts · 36
Foundation complete, erection pending — highest-value idle front.
Shivlakha 59/0, 60/0, 62/0, 63/0 +6 10
Vrajvani 11/2, 12/0, 12/1, 12A/0 +2 6
Gedi 14/4, 16/7, 17/1, 18/0 +1 5
Sai 28/0, 29/0, 30/0, 31/0 4
Mauvana 7/0, 7/3, 10/7 3
Dabhunda 24/3, 24A/0, 24A/1 3
Umaiya 20A/0, 22/0 2
Stringing-ready sections · 62
Towers erected — needs crossing clearances before stringing.
Umaiya 18A/8, 19/0, 19/1, 19/2 +16 20
Sai 25/4, 26/0, 26/1, 27/0 +4 8
Govindpar 43/0, 44/0, 45/0, 46/0 +4 8
Gedi 13/2, 14/2, 14/3, 18/1 +3 7
Selari 18A/2, 18A/3, 18A/4, 18A/5 +2 6
Mauvana 7/1, 7/2, 7/4, 7/5 +1 5
Vrajvani 11/1, 11/3, 11/4, 11/5 4

Latest update Δ · 400kV Z2 – Lakadia

Comparison: 10-Sep-26 → 13-Sep-26 · 3 days · computed from the loaded trackers
0 141 → 141 Additional RoW secured
0 98 → 98 Foundation / pile completed
0 2 → 2 Foundation WIP
0 62 → 62 Tower erections completed

Location-level changes 3

LocationVillageWhat changed
36/0Khirai Crossing GETCO - 66kV Powerline NH CrossingGETCO - 66kV Powerline NH Crossing
37/0Khirai Crossing GETCO - 66kV Powerline NH CrossingGETCO - 66kV Powerline NH Crossing
71/0Shivlakha Land PrivateIn Adani's Lakadia S/S
Location Register
232 of 232 locations · 23 columns
Records shown: 232 of 232
Location#VillagePackageContractorChainageTower TypeKindClass of LandRoWRoW Sub-issueFoundationErectionStringingForestCrossingSpan (m)DeviationLatitudeLongitudeCurrent StatusRemarksRemarks 2
1/01RIL ParcelPkg-1JSL0.00 kmUnknownRILRoW SecuredNone - front availablePile doneNotStartedNotStarted301.423.8523370.98914
1/12RIL ParcelPkg-1JSL0.30 kmUnknownRILRoW SecuredNone - front availablePile doneNotStartedNotStarted350.223.8523770.98594
1/23RIL ParcelPkg-1JSL0.65 kmUnknownRILRoW SecuredNone - front availablePile doneNotStartedNotStarted364.923.8524170.98274
1/34RIL ParcelPkg-1JSL1.02 kmUnknownRILRoW SecuredNone - front availablePile doneNotStartedNotStarted376.123.8524570.97915
1/45RIL ParcelPkg-1JSL1.39 kmUnknownRILRoW SecuredNone - front availablePile doneNotStartedNotStarted367.823.8525070.97545
1/56RIL ParcelPkg-1JSL1.76 kmUnknownRILRoW SecuredNone - front availablePile doneNotStartedNotStarted377.823.8525570.97184
1/67RIL ParcelPkg-1JSL2.14 kmUnknownRILRoW SecuredNone - front availablePile doneNotStartedNotStarted380.323.8526070.96812
1/78RIL ParcelPkg-1JSL2.52 kmUnknownRILRoW SecuredNone - front availablePile doneNotStartedNotStarted377.823.8526470.96438
1/89RIL ParcelPkg-1JSL2.90 kmUnknownRILRoW SecuredNone - front availablePile doneNotStartedNotStarted350.223.8526970.96067
1/910RIL ParcelPkg-1JSL3.25 kmUnknownRILRoW SecuredNone - front availablePile doneNotStartedNotStarted363.623.8527370.95722
2/011RIL ParcelPkg-1JSL3.61 kmTensionRILRoW SecuredWaterlogging - temporarily on holdNotStartedNotStartedNotStarted328.823.8527870.95365
2/1N12RIL ParcelPkg-1JSL3.94 kmSuspensionRILRoW SecuredWaterlogging - temporarily on holdNotStartedNotStartedNotStarted380.923.8529870.95043
2A/013RIL ParcelPkg-1JSL4.32 kmUnknownRILRoW SecuredWaterlogging - temporarily on holdNotStartedNotStartedNotStarted185.423.8532270.94669
2B/014RIL ParcelPkg-1JSL4.51 kmUnknownRILRoW SecuredWaterlogging - temporarily on holdNotStartedNotStartedNotStarted362.723.8545070.94551
4/0N15RIL ParcelPkg-1JSL4.87 kmUnknownRILRoW SecuredWaterlogging - temporarily on holdNotStartedNotStartedNotStarted343.523.8576870.94476
4/1N16RIL ParcelPkg-1JSL5.21 kmUnknownRILRoW SecuredWaterlogging - temporarily on holdNotStartedNotStartedNotStarted341.623.8604070.94315
4/2N17RIL ParcelPkg-1JSL5.55 kmUnknownRILRoW SecuredNone - front availablePile doneNotStartedNotStarted34223.8631870.94150
4A/0N18RIL ParcelPkg-1JSL5.89 kmUnknownRILRoW SecuredNone - front availablePile doneNotStartedNotStarted313.623.8658070.93995
4A/1N19RIL ParcelPkg-1JSL6.21 kmUnknownRILRoW SecuredNone - front availablePile doneNotStartedNotStarted322.623.8678070.93777
4A/2N20RIL ParcelPkg-1JSL6.53 kmUnknownRILRoW SecuredNone - front availablePile doneNotStartedNotStarted330.423.8698670.93553
4A/3N21RIL ParcelPkg-1JSL6.86 kmUnknownRILRoW SecuredNone - front availablePile doneNotStartedNotStarted325.323.8719670.93324
4B/0N22RIL ParcelPkg-1JSL7.19 kmUnknownRILRoW SecuredWaterlogging - temporarily on holdNotStartedNotStartedNotStarted318.923.8740470.93098
4C/0N23RIL ParcelPkg-1JSL7.51 kmUnknownRILRoW SecuredWaterlogging - temporarily on holdNotStartedNotStartedNotStarted243.123.8757970.92850
4C/1N24RIL ParcelPkg-1JSL7.75 kmUnknownRILRoW SecuredWaterlogging - temporarily on holdNotStartedNotStartedNotStarted24423.8768770.92589
4D/0N25RIL ParcelPkg-1JSL7.99 kmUnknownRILRoW SecuredWaterlogging - temporarily on holdNotStartedNotStartedNotStarted340.823.8776070.92413
4E/0N26CreekPkg-1JSL8.33 kmUnknownGovernmentRoW SecuredWaterlogging - temporarily on holdNotStartedNotStartedNotStarted424.723.8773070.92080
5/0N27CreekPkg-1JSL8.76 kmUnknownGovernmentRoW SecuredWaterlogging - temporarily on holdNotStartedNotStartedNotStarted320.123.8748670.91759
5/1N28CreekPkg-1JSL9.08 kmUnknownGovernmentRoW SecuredWaterlogging - temporarily on holdNotStartedNotStartedNotStarted211.723.8721170.91666
6/0N29CreekPkg-1JSL9.29 kmUnknownGovernmentRoW SecuredWaterlogging - temporarily on holdNotStartedNotStartedNotStarted390.223.8702970.91605
6/130MauvanaPkg-1JSL9.68 kmTensionGovernmentRoW SecuredWaterlogging - temporarily on holdNotStartedNotStartedNotStarted389.123.8668070.91564
6/231MauvanaPkg-1JSL10.07 kmTensionPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStarted420.423.8633470.91506
6/332MauvanaPkg-1JSL10.49 kmTensionPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStarted378.823.8595770.91475
6/433MauvanaPkg-1JSL10.87 kmTensionPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStarted334.923.8562270.91409
6/534MauvanaPkg-1JSL11.20 kmSuspensionPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStarted439.123.8532270.91375
6/635MauvanaPkg-1JSL11.64 kmTensionPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStarted385.923.8490970.91328
6/736MauvanaPkg-1JSL12.03 kmTensionPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStarted394.223.8458870.91262
7/037MauvanaPkg-1JSL12.42 kmTensionGovernmentRoW SecuredNone - front availableCompletedNotStartedNotStarted339.623.8423470.91246
7/138MauvanaPkg-1JSL12.76 kmSuspensionGovernmentRoW SecuredNone - front availableCompletedCompletedNotStarted336.823.8398470.91005
7/239MauvanaPkg-1JSL13.10 kmSuspensionGovernmentRoW SecuredNone - front availableCompletedCompletedNotStarted397.423.8377870.90806
7/340MauvanaPkg-1JSL13.50 kmSuspensionGovernmentRoW SecuredNone - front availableCompletedNotStartedNotStarted37123.8351070.90547
7/441MauvanaPkg-1JSL13.87 kmSuspensionGovernmentRoW SecuredNone - front availableCompletedCompletedNotStarted406.623.8326070.90306
7/542MauvanaPkg-1JSL14.27 kmSuspensionGovernmentRoW SecuredNone - front availableCompletedCompletedNotStarted399.423.8298670.90041
8/043MauvanaPkg-1JSL14.67 kmTensionPrivateRoW SecuredNone - front availableNotStartedNotStartedNotStarted225.123.8271770.89781
9/044MauvanaPkg-1JSL14.90 kmTensionGovernmentRoW SecuredNone - front availableNotStartedNotStartedNotStarted39223.8253270.89691
9/145MauvanaPkg-1JSL15.29 kmSuspensionPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStarted370.823.8236270.89353
9/246MauvanaPkg-1JSL15.66 kmSuspensionGovernmentRoW SecuredNone - front availableCompletedCompletedNotStarted349.823.8220270.89034
9/347MauvanaPkg-1JSL16.01 kmSuspensionPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStarted476.823.8205070.88733
9/448MauvanaPkg-1JSL16.49 kmSuspensionPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStarted341.223.8184370.88322
9/549MauvanaPkg-1JSL16.83 kmSuspensionPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStarted494.723.8169570.88028
9/650MauvanaPkg-1JSL17.32 kmSuspensionPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStarted294.423.8148070.87602
10/051MauvanaPkg-1JSL17.62 kmDB(00-15)+03TensionPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStarted434.523.8135370.87349
10/152MauvanaPkg-1JSL18.05 kmDA(00-02)+09UnknownPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStarted288.623.8123570.86941
10/253MauvanaPkg-1JSL18.34 kmDA(00-02)+03SuspensionPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStarted39523.8115770.86671
10/354MauvanaPkg-1JSL18.74 kmDA(00-02)+03SuspensionPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStarted438.123.8105170.86300
10/455MauvanaPkg-1JSL19.17 kmDA(00-02)+03SuspensionPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStarted38823.8093270.85890
10/556MauvanaPkg-1JSL19.56 kmDA(00-02)+03SuspensionPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStarted376.323.8082770.85526
10/657MauvanaPkg-1JSL19.94 kmDA(00-02)+03SuspensionPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStarted385.623.8072670.85173
10/758MauvanaPkg-1JSL20.32 kmDA(00-02)+03SuspensionGovernmentRoW SecuredNone - front availableCompletedNotStartedNotStarted430.323.8062270.84812
10/859MauvanaPkg-1JSL20.75 kmDA(00-02)+03SuspensionPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStarted401.923.8050570.84408
10/960MauvanaPkg-1JSL21.16 kmDB(00-15)+00TensionPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStarted414.423.8039770.84031
10/1061MauvanaPkg-1JSL21.57 kmDA(00-02)+03SuspensionPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStarted363.423.8028570.83643
10/1162MauvanaPkg-1JSL21.93 kmDA(00-02)+00SuspensionPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStarted420.423.8018670.83302
10/1263MauvanaPkg-1JSL22.35 kmDA(00-02)+03SuspensionPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStarted391.523.8007370.82908
10/1364MauvanaPkg-1JSL22.75 kmDA(00-02)+03SuspensionGovernmentRoW SecuredNone - front availableNotStartedNotStartedNotStarted413.723.7996770.82541
10/1465MauvanaPkg-1JSL23.16 kmDA(00-02)+00SuspensionPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStarted392.723.7985570.82153
10/1566BelaPkg-1JSL23.55 kmDA(00-02)+03SuspensionPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStarted405.623.7974970.81785
10/1667BelaPkg-1JSL23.96 kmDA(00-02)+00SuspensionPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStarted414.323.7963970.81405
10/1768VrajvaniPkg-1JSL24.37 kmDA(00-02)+06SuspensionPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStarted417.823.7952770.81017
11/069VrajvaniPkg-1JSL24.79 kmDD(30-60)+00TensionPrivateRoW SecuredMRC formation to be expeditedNotStartedNotStartedNotStarted36523.7941470.80625
11/170VrajvaniPkg-1JSL25.16 kmDA(00-02)+00SuspensionGovernmentRoW SecuredNone - front availableCompletedCompletedNotStarted379.323.7916070.80398
11/271VrajvaniPkg-1JSL25.53 kmDA(00-02)+00SuspensionPrivateRoW SecuredNone - front availableCompletedNotStartedNotStarted348.123.7889670.80161
11/372VrajvaniPkg-1JSL25.88 kmDA(00-02)+00SuspensionGovernmentRoW SecuredNone - front availableCompletedCompletedNotStarted398.223.7865470.79945
11/473VrajvaniPkg-1JSL26.28 kmDA(00-02)+00SuspensionGovernmentRoW SecuredNone - front availableCompletedCompletedNotStarted375.623.7837770.79697
11/574VrajvaniPkg-1JSL26.66 kmDA(00-02)+00SuspensionGovernmentRoW SecuredNone - front availableCompletedCompletedNotStarted322.623.7811670.79463
12/075VrajvaniPkg-1JSL26.98 kmDD(30-60)+00TensionGovernmentRoW SecuredNone - front availableCompletedNotStartedNotStarted393.623.7791770.79285
12/176VrajvaniPkg-1JSL27.37 kmDA(00-02)+03SuspensionPrivateRoW SecuredNone - front availableCompletedNotStartedNotStarted395.923.7755270.79318
12A/077VrajvaniPkg-1JSL27.77 kmTensionPrivateRoW SecuredNone - front availableCompletedNotStartedNotStarted429.323.7718670.79351
12A/178VrajvaniPkg-1JSL28.20 kmSuspensionPrivateRoW SecuredNone - front availableCompletedNotStartedNotStarted37023.7681770.79477
12A/279VrajvaniPkg-1JSL28.57 kmSuspensionPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStarted412.923.7650070.79586
13/080VrajvaniPkg-1JSL28.98 kmTensionPrivateRoW SecuredNone - front availableCompletedNotStartedNotStarted366.223.7614570.79707
13/181VrajvaniPkg-1JSL29.35 kmSuspensionPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStarted336.823.7582670.79619
13/282GediPkg-1JSL29.68 kmSuspensionGovernmentRoW SecuredNone - front availableCompletedCompletedNotStarted394.623.7553270.79538
13/383GediPkg-1JSL30.08 kmSuspensionPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStarted325.723.7518870.79442
13/484GediPkg-1JSL30.40 kmSuspensionGovernmentRoW SecuredNone - front availableWIPNotStartedNotStarted429.923.7490470.79364
14/085GediPkg-1JSL30.83 kmTensionPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStarted363.423.7453070.79260
14/186GediPkg-1JSL31.20 kmSuspensionPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStarted338.423.7422670.79391
14/287GediPkg-1JSL31.54 kmSuspensionGovernmentRoW SecuredNone - front availableCompletedCompletedNotStarted380.723.7394370.79513
14/388GediPkg-1JSL31.92 kmSuspensionGovernmentRoW SecuredNone - front availableCompletedCompletedNotStarted349.523.7362470.79650
14/489GediPkg-1JSL32.27 kmSuspensionGovernmentRoW SecuredNone - front availableCompletedNotStartedNotStarted338.923.7333270.79777
14/590FatehgarhPkg-1JSL32.60 kmSuspensionPrivateRoW SecuredMRC formation to be expeditedNotStartedNotStartedNotStarted344.123.7304970.79899
15/091FatehgarhPkg-1JSL32.95 kmTensionPrivateRoW SecuredMRC formation to be expeditedNotStartedNotStartedNotStarted365.523.7276170.80024
15/192GediPkg-1JSL33.31 kmSuspensionPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStarted37923.7248970.79821
15/293GediPkg-1JSL33.69 kmSuspensionPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStarted425.423.7219670.79604
16/094GediPkg-1JSL34.12 kmSuspensionPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStarted345.923.7189170.79377
16/195GediPkg-1JSL34.46 kmSuspensionPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStarted384.323.7159670.79150
16/296GediPkg-1JSL34.85 kmSuspensionPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStarted382.623.7135470.78963
16/397GediPkg-1JSL35.23 kmSuspensionPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStarted378.123.7107370.78747
16/498GediPkg-1JSL35.61 kmSuspensionPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStarted388.923.7079570.78533
16/599GediPkg-1JSL36.00 kmSuspensionGovernmentRoW SecuredNone - front availableNotStartedNotStartedNotStarted432.623.7051070.78312
16/6100GediPkg-1JSL36.43 kmSuspensionPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStarted329.123.7024270.78106
16/7101GediPkg-1JSL36.76 kmSuspensionGovernmentRoW SecuredNone - front availableCompletedNotStartedNotStarted375.723.6995070.77881
17/0102GediPkg-1JSL37.14 kmTensionGovernmentRoW SecuredWaterlogging - temporarily on holdNotStartedNotStartedNotStarted40623.6967470.77668
17/1103GediPkg-1JSL37.54 kmSuspensionGovernmentRoW SecuredNone - front availableCompletedNotStartedNotStarted388.423.6932370.77559
17/2104GediPkg-1JSL37.93 kmSuspensionPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStarted385.723.6898770.77455
17/3105GediPkg-1JSL38.32 kmSuspensionPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStarted389.823.6865370.77351
17/4106GediPkg-1JSL38.71 kmSuspensionPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStarted373.423.6831670.77246
17/5107GediPkg-1JSL39.08 kmSuspensionPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStarted384.323.6799370.77146
18/0108GediPkg-1JSL39.46 kmTensionGovernmentRoW SecuredNone - front availableCompletedNotStartedNotStarted360.723.6766170.77042
18/1109GediPkg-2TLL39.82 kmSuspensionGovernmentRoW SecuredNone - front availableCompletedCompletedNotStarted350.323.6733870.77007
18/2110GediPkg-2TLL40.17 kmSuspensionGovernmentRoW SecuredNone - front availableCompletedCompletedNotStarted401.323.6702470.76973
18/3111GediPkg-2TLL40.58 kmSuspensionGovernmentRoW SecuredNone - front availableCompletedCompletedNotStarted383.723.6666570.76935
18A/0112GediPkg-2TLL40.96 kmTensionGovernmentRoW SecuredNone - front availableCompletedCompletedNotStarted397.523.6632270.76897
18A/1113GediPkg-2TLL41.36 kmSuspensionPrivateRoW SecuredNone - front availableCompletedNotStartedNotStarted397.523.6596570.76858
18A/2114SelariPkg-2TLL41.75 kmSuspensionPrivateRoW SecuredNone - front availableCompletedCompletedNotStarted397.523.6561170.76819
18A/3115SelariPkg-2TLL42.15 kmSuspensionPrivateRoW SecuredNone - front availableCompletedCompletedNotStarted397.523.6526470.76781
18A/4116SelariPkg-2TLL42.55 kmSuspensionPrivateRoW SecuredNone - front availableCompletedCompletedNotStarted397.423.6489770.76741
18A/5117SelariPkg-2TLL42.95 kmUnknownPrivateRoW SecuredNone - front availableCompletedCompletedNotStarted397.523.6453270.76701
18A/6118SelariPkg-2TLL43.34 kmSuspensionGovernmentRoW SecuredNone - front availableCompletedCompletedNotStarted397.523.6417370.76662
18A/7119SelariPkg-2TLL43.74 kmSuspensionPrivateRoW SecuredNone - front availableCompletedCompletedNotStarted397.523.6379970.76621
18A/8120UmaiyaPkg-2TLL44.14 kmSuspensionPrivateRoW SecuredNone - front availableCompletedCompletedNotStarted397.523.6345670.76583
19/0121UmaiyaPkg-2TLL44.54 kmTensionGovernmentRoW SecuredNone - front availableCompletedCompletedNotStarted37523.6312570.76547
19/1122UmaiyaPkg-2TLL44.91 kmSuspensionGovernmentRoW SecuredNone - front availableCompletedCompletedNotStarted373.723.6282470.76376
19/2123UmaiyaPkg-2TLL45.29 kmSuspensionGovernmentRoW SecuredNone - front availableCompletedCompletedNotStarted38023.6250270.76193
19/3124UmaiyaPkg-2TLL45.67 kmSuspensionGovernmentRoW SecuredNone - front availableCompletedCompletedNotStarted375.823.6222170.76033
19/4125UmaiyaPkg-2TLL46.04 kmSuspensionGovernmentRoW SecuredNone - front availableCompletedCompletedNotStarted38123.6192170.75863
20/0126UmaiyaPkg-2TLL46.42 kmTensionGovernmentRoW SecuredNone - front availableCompletedCompletedNotStarted395.223.6162570.75694
20/1127UmaiyaPkg-2TLL46.82 kmSuspensionGovernmentRoW SecuredNone - front availableCompletedCompletedNotStarted380.523.6132570.75508
20/2128UmaiyaPkg-2TLL47.20 kmSuspensionGovernmentRoW SecuredNone - front availableCompletedCompletedNotStarted378.923.6107870.75354
20/3129UmaiyaPkg-2TLL47.58 kmSuspensionPrivateRoW SecuredNone - front availableCompletedCompletedNotStarted38323.6078170.75169
20/4130UmaiyaPkg-2TLL47.96 kmSuspensionGovernmentRoW SecuredNone - front availableCompletedCompletedNotStarted382.723.6050670.74998
20/5131UmaiyaPkg-2TLL48.34 kmSuspensionGovernmentRoW SecuredNone - front availableCompletedCompletedNotStarted334.923.6019470.74804
20/6132UmaiyaPkg-2TLL48.68 kmSuspensionGovernmentRoW SecuredNone - front availableCompletedCompletedNotStarted339.723.5988370.74610
20/7133UmaiyaPkg-2TLL49.02 kmSuspensionGovernmentRoW SecuredNone - front availableCompletedCompletedNotStarted387.723.5956570.74412
20/8134UmaiyaPkg-2TLL49.41 kmSuspensionGovernmentRoW SecuredNone - front availableCompletedCompletedNotStarted385.323.5926770.74227
20A/0135UmaiyaPkg-2TLL49.79 kmTensionPrivateRoW SecuredNone - front availableCompletedNotStartedNotStarted387.423.5899470.74057
21/0136UmaiyaPkg-2TLL50.18 kmTensionGovernmentRoW SecuredNone - front availableCompletedCompletedNotStarted361.123.5872870.73809
21/1137UmaiyaPkg-2TLL50.54 kmSuspensionPrivateRoW SecuredNone - front availableCompletedCompletedNotStarted33823.5844670.73709
21/2138UmaiyaPkg-2TLL50.88 kmSuspensionPrivateRoW SecuredNone - front availableCompletedCompletedNotStarted330.923.5814070.73601
21/3139UmaiyaPkg-2TLL51.21 kmSuspensionPrivateRoW SecuredNone - front availableCompletedCompletedNotStarted310.323.5784770.73497
22/0140UmaiyaPkg-2TLL51.52 kmTensionPrivateRoW SecuredNone - front availableCompletedNotStartedNotStarted411.323.5755470.73393
22/1141UmaiyaPkg-2TLL51.93 kmSuspensionPrivateRoW SecuredNone - front availableCompletedCompletedNotStarted413.823.5721070.73272
22/2142PragparPkg-2TLL52.34 kmSuspensionPrivateNotice issued / MRCOther (see remarks)NotStartedNotStartedNotStarted413.923.5686070.73149
22/3143PragparPkg-2TLL52.76 kmSuspensionPrivateNotice issued / MRCOther (see remarks)NotStartedNotStartedNotStarted418.923.5650570.73025
22/4144PragparPkg-2TLL53.18 kmSuspensionGovernmentRoW SecuredNone - front availableCompletedCompletedNotStartedGETCO Powerline Crossing353.823.5614770.72899
22/5145PragparPkg-2TLL53.53 kmSuspensionPrivateNotice issued / MRCOther (see remarks)NotStartedNotStartedNotStartedGETCO Powerline Crossing416.423.5583070.72787
22/6146PragparPkg-2TLL53.95 kmSuspensionPrivateNotice issued / MRCOther (see remarks)NotStartedNotStartedNotStarted41323.5548470.72666
22/7147PragparPkg-2TLL54.36 kmUnknownPrivateNotice issued / MRCOther (see remarks)NotStartedNotStartedNotStarted406.623.5513470.72543
23/0148TindalvaPkg-2TLL54.77 kmUnknownPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStarted443.123.5478670.72420
23/1149TindalvaPkg-2TLL55.21 kmSuspensionPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStarted547.823.5451770.72186
23A/0150TindalvaPkg-2TLL55.76 kmTensionPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStarted547.823.5421470.71921
23A/1151TindalvaPkg-2TLL56.30 kmSuspensionPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStarted547.923.5401670.71641
24/0152TindalvaPkg-2TLL56.85 kmTensionGovernmentRoW SecuredNone - front availableCompletedCompletedNotStarted37223.5377270.71297
24/1153TindalvaPkg-2TLL57.22 kmSuspensionPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStarted372.923.5342370.71111
24/2154TindalvaPkg-2TLL57.60 kmSuspensionPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStarted293.123.5312870.70952
24/3155DabhundaPkg-2TLL57.89 kmSuspensionGovernmentRoW SecuredNone - front availableCompletedNotStartedNotStarted153.123.5284570.70800
24A/0156DabhundaPkg-2TLL58.04 kmTensionGovernmentRoW SecuredNone - front availableCompletedNotStartedNotStarted153.123.5254170.70637
24A/1157DabhundaPkg-2TLL58.20 kmSuspensionGovernmentRoW SecuredNone - front availableCompletedNotStartedNotStarted153.123.5227270.70422
24A/2158DabhundaPkg-2TLL58.35 kmSuspensionPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStarted153.123.5205070.70245
24A/3159DabhundaPkg-2TLL58.50 kmSuspensionPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStarted153.123.5179770.70044
25/0160DabhundaPkg-2TLL58.66 kmTensionGovernmentRoW SecuredPolice / SDM / Mamlatdar support requiredNotStartedNotStartedNotStarted341.523.5154070.69839
25/1161DabhundaPkg-2TLL59.00 kmSuspensionGovernmentRoW SecuredPolice / SDM / Mamlatdar support requiredNotStartedNotStartedNotStarted374.623.5138770.69631
25/2162DabhundaPkg-2TLL59.37 kmSuspensionPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStarted41023.5124670.69437
25/3163SaiPkg-2TLL59.78 kmSuspensionPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStarted409.423.5099570.69096
25/4164SaiPkg-2TLL60.19 kmSuspensionGovernmentRoW SecuredNone - front availableCompletedCompletedNotStarted373.323.5079770.68826
26/0165SaiPkg-2TLL60.56 kmTensionGovernmentRoW SecuredNone - front availableCompletedCompletedNotStarted289.323.5058570.68536
26/1166SaiPkg-2TLL60.85 kmUnknownGovernmentRoW SecuredNone - front availableCompletedCompletedNotStarted11kv line shifting587.923.5042270.68364
27/0167SaiPkg-2TLL61.44 kmUnknownGovernmentRoW SecuredNone - front availableCompletedCompletedNotStarted115.723.5024170.68172
28/0168SaiPkg-2TLL61.56 kmUnknownGovernmentRoW SecuredNone - front availableCompletedNotStartedNotStartedPGCIL - 765kV under crossing90.523.5013270.68184
29/0169SaiPkg-2TLL61.65 kmUnknownGovernmentRoW SecuredNone - front availableCompletedNotStartedNotStartedPGCIL - 765kV under crossing63.723.5005670.68222
30/0170SaiPkg-2TLL61.71 kmUnknownGovernmentRoW SecuredNone - front availableCompletedNotStartedNotStartedAdani - 500kV crossing61.423.4999170.68323
31/0171SaiPkg-2TLL61.77 kmUnknownGovernmentRoW SecuredNone - front availableCompletedNotStartedNotStartedAdani - 500kV crossing84.523.4992970.68372
32/0172SaiPkg-2TLL61.86 kmUnknownGovernmentRoW SecuredNone - front availableCompletedCompletedNotStartedAdani - 500kV crossing147.723.4978470.68348
33/0173SaiPkg-2TLL62.01 kmUnknownPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStartedAdani - 500kV crossing Adjacent tower126923.4943670.68178
34/0174SaiPkg-2TLL63.27 kmUnknownGovernmentRoW SecuredNone - front availableCompletedCompletedNotStarted430.423.4921070.67831
34/1175SaiPkg-2TLL63.70 kmSuspensionGovernmentRoW SecuredNone - front availableCompletedCompletedNotStarted40523.4884870.67622
34/2176SaiPkg-2TLL64.11 kmSuspensionPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStarted407.323.4854470.67446
34/3177SaiPkg-2TLL64.52 kmSuspensionPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStarted424.823.4822670.67263
34/4178SaiPkg-2TLL64.94 kmTensionPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStarted407.423.4787770.67062
34/5179SaiPkg-2TLL65.35 kmSuspensionGovernmentRoW SecuredNone - front availableCompletedCompletedNotStarted215.523.4750770.66848
34/6180SaiPkg-2TLL65.56 kmSuspensionPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStarted215.623.4721270.66678
35/0181KhiraiPkg-2TLL65.78 kmTensionGovernmentRoW SecuredNone - front availableCompletedNotStartedNotStarted341.423.4687770.66485
35/1182KhiraiPkg-2TLL66.12 kmSuspensionGovernmentRoW SecuredNone - front availableCompletedCompletedNotStarted292.923.4659770.66255
35/2183KhiraiPkg-2TLL66.41 kmSuspensionPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStarted359.223.4635370.66055
36/0184KhiraiPkg-2TLL66.77 kmTensionPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStartedGETCO - 66kV Powerline NH Crossing314.923.4619270.65923
37/0185KhiraiPkg-2TLL67.09 kmUnknownPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStartedGETCO - 66kV Powerline NH Crossing360.923.4607470.65721
37/1186KhiraiPkg-2TLL67.45 kmUnknownPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStarted360.923.4591470.65466
37/2187KhiraiPkg-2TLL67.81 kmSuspensionPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStarted66kV S/C Line360.923.4567970.65089
39/0188KhiraiPkg-2TLL68.17 kmUnknownPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStarted66kV S/C Line317.223.4549070.64789
39/1189BadargadhPkg-2TLL68.49 kmUnknownPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStarted375.323.4531170.64566
39/2190BadargadhPkg-2TLL68.86 kmUnknownPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStarted377.423.4508070.64278
39/3191BadargadhPkg-2TLL69.24 kmUnknownPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStarted384.723.4486870.64015
39/4192BadargadhPkg-2TLL69.63 kmUnknownPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStarted380.523.4465970.63755
39/5193BadargadhPkg-2TLL70.01 kmUnknownPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStarted399.923.4443270.63473
40/0194BadargadhPkg-2TLL70.41 kmUnknownGovernmentRoW SecuredNone - front availableCompletedNotStartedNotStartedGETCO - 66kV Powerline210.723.4416570.63141
41/0195BadargadhPkg-2TLL70.62 kmUnknownPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStartedGETCO - 66kV Powerline255.823.4413470.62937
41/1196BadargadhPkg-2TLL70.87 kmUnknownPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStarted285.123.4392470.62836
42/0197BadargadhPkg-2TLL71.16 kmUnknownGovernmentRoW SecuredNone - front availableCompletedNotStartedNotStarted289.923.4368670.62721
42/1198GovindparPkg-2TLL71.45 kmUnknownPrivateNotice issued / MRCOther (see remarks)NotStartedNotStartedNotStarted342.823.4342270.62567
43/0199GovindparPkg-2TLL71.79 kmUnknownGovernmentRoW SecuredNone - front availableCompletedCompletedNotStartedAdjacent to crossing179.323.4306970.62361
44/0200GovindparPkg-2TLL71.97 kmUnknownGovernmentRoW SecuredNone - front availableCompletedCompletedNotStartedGETCO - 400kV X 2nos, PGCIL - 400kV X 1no165.723.4270370.62415
45/0201GovindparPkg-2TLL72.14 kmUnknownGovernmentRoW SecuredNone - front availableCompletedCompletedNotStartedGETCO - 400kV X 2nos, PGCIL - 400kV X 1no, Adani - 400kV280.623.4246570.62622
46/0202GovindparPkg-2TLL72.42 kmUnknownGovernmentRoW SecuredNone - front availableCompletedCompletedNotStartedAdani - 400kV200.523.4229270.62808
47/0203GovindparPkg-2TLL72.62 kmUnknownGovernmentRoW SecuredNone - front availableCompletedCompletedNotStartedAdjacent to crossing375.623.4193470.62764
48/0204GovindparPkg-2TLL72.99 kmUnknownGovernmentRoW SecuredNone - front availableCompletedCompletedNotStartedAdjacent to crossing661.823.4173070.62707
49/0205GovindparPkg-2TLL73.65 kmUnknownGovernmentRoW SecuredNone - front availableCompletedCompletedNotStarted2XHPCL, 1XHMEL gas pileline598.823.4138670.62727
50/0206GovindparPkg-2TLL74.25 kmUnknownPrivateRoW SecuredNone - front availableWIPNotStartedNotStarted2XHPCL, 1XHMEL gas pileline419.423.4110570.62822
50/1207GovindparPkg-2TLL74.67 kmUnknownGovernmentRoW SecuredNone - front availableCompletedCompletedNotStartedAdjacent to crossing448.823.4079870.62819
51/0208ShivlakhaPkg-2TLL75.12 kmUnknownPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStarted90.523.4035970.62814
52/0209ShivlakhaPkg-2TLL75.21 kmUnknownPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStartedAdani - 765kV crossing120.423.4028870.62844
53/0210ShivlakhaPkg-2TLL75.33 kmUnknownPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStartedAdani - 765kV crossing87.923.4018770.62898
54/0211ShivlakhaPkg-2TLL75.42 kmUnknownPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStarted419.723.4012270.62935
55/0212ShivlakhaPkg-2TLL75.84 kmUnknownPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStarted452.923.3986170.62909
55/1213ShivlakhaPkg-2TLL76.29 kmUnknownPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStarted376.123.3968070.62523
55/2214ShivlakhaPkg-2TLL76.67 kmUnknownPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStarted209.523.3954470.62231
55A/0215ShivlakhaPkg-2TLL76.88 kmUnknownPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStarted209.523.3938470.61891
56/0216ShivlakhaPkg-2TLL77.09 kmUnknownPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStarted113.823.3924570.61781
57/0217ShivlakhaPkg-2TLL77.20 kmUnknownPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStartedPGCIL - 765kV under crossing85.723.3914670.61768
58/0218ShivlakhaPkg-2TLL77.29 kmUnknownPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStartedPGCIL - 765kV under crossing143.123.3906670.61767
59/0219ShivlakhaPkg-2TLL77.43 kmUnknownGovernmentRoW SecuredNone - front availableCompletedNotStartedNotStartedAdjacent to crossing123.423.3892570.61795
60/0220ShivlakhaPkg-2TLL77.55 kmUnknownGovernmentRoW SecuredNone - front availableCompletedNotStartedNotStartedSterlite - 765kV undercrossing65.323.3879370.61753
61/0221ShivlakhaPkg-2TLL77.62 kmUnknownGovernmentRoW SecuredPolice / SDM / Mamlatdar support requiredNotStartedNotStartedNotStartedSterlite - 765kV undercrossing9023.3874670.61675
62/0222ShivlakhaPkg-2TLL77.71 kmUnknownGovernmentRoW SecuredNone - front availableCompletedNotStartedNotStartedAdjacent to crossing126.323.3869070.61567
63/0223ShivlakhaPkg-2TLL77.84 kmUnknownGovernmentRoW SecuredNone - front availableCompletedNotStartedNotStarted303.223.3855870.61307
64/0224ShivlakhaPkg-2TLL78.14 kmUnknownGovernmentRoW SecuredNone - front availableCompletedNotStartedNotStarted245.523.3844470.61101
65/0225ShivlakhaPkg-2TLL78.38 kmUnknownGovernmentRoW SecuredNone - front availableCompletedNotStartedNotStarted393.523.3820370.60818
66/0226ShivlakhaPkg-2TLL78.78 kmUnknownGovernmentRoW SecuredNone - front availableCompletedNotStartedNotStarted414.523.3791770.60559
67/0227ShivlakhaPkg-2TLL79.19 kmUnknownPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStarted408.623.3794070.60132
68/0228ShivlakhaPkg-2TLL79.60 kmUnknownGovernmentRoW SecuredNone - front availableCompletedNotStartedNotStarted435.723.3808770.59764
69/0229ShivlakhaPkg-2TLL80.04 kmUnknownGovernmentRoW SecuredNone - front availableCompletedNotStartedNotStarted283.223.3829770.59629
70/0230ShivlakhaPkg-2TLL80.32 kmUnknownGovernmentRoW SecuredNone - front availableCompletedCompletedNotStartedAdani KPS-III to Lakadia180.723.3861970.59436
70A/0231ShivlakhaPkg-2TLL80.50 kmUnknownPrivateNotice issued / MRCMRC formation to be expeditedNotStartedNotStartedNotStartedAdani KPS-III to Lakadia180.823.3881270.59410
71/0232ShivlakhaPkg-2TLL80.68 kmUnknownPrivateRoW SecuredNone - front availableCompletedNotStartedNotStartedAdani KPS-III to Lakadia23.3892770.59340
Page 1 of 1 showing 232 rows · click a row for the full record
Data Entry
Editing 232 of 232 locations · whole project
Records shown: 232 of 232
13 columns shown · scroll sideways for more
#read-onlyLocationread-onlyVillageread-onlyPackageread-onlyRoW StatusRoW BlockerFoundationErectionStringingPending SinceAgeingread-onlyCrossing at LocationCurrent status / remarks
11/0
0.00 km
RIL ParcelPkg-1
21/1
0.30 km
RIL ParcelPkg-1
31/2
0.65 km
RIL ParcelPkg-1
41/3
1.02 km
RIL ParcelPkg-1
51/4
1.39 km
RIL ParcelPkg-1
61/5
1.76 km
RIL ParcelPkg-1
71/6
2.14 km
RIL ParcelPkg-1
81/7
2.52 km
RIL ParcelPkg-1
91/8
2.90 km
RIL ParcelPkg-1
101/9
3.25 km
RIL ParcelPkg-1
112/0
3.61 km
RIL ParcelPkg-1
122/1N
3.94 km
RIL ParcelPkg-1
132A/0
4.32 km
RIL ParcelPkg-1
142B/0
4.51 km
RIL ParcelPkg-1
154/0N
4.87 km
RIL ParcelPkg-1
164/1N
5.21 km
RIL ParcelPkg-1
174/2N
5.55 km
RIL ParcelPkg-1
184A/0N
5.89 km
RIL ParcelPkg-1
194A/1N
6.21 km
RIL ParcelPkg-1
204A/2N
6.53 km
RIL ParcelPkg-1
214A/3N
6.86 km
RIL ParcelPkg-1
224B/0N
7.19 km
RIL ParcelPkg-1
234C/0N
7.51 km
RIL ParcelPkg-1
244C/1N
7.75 km
RIL ParcelPkg-1
254D/0N
7.99 km
RIL ParcelPkg-1
264E/0N
8.33 km
CreekPkg-1
275/0N
8.76 km
CreekPkg-1
285/1N
9.08 km
CreekPkg-1
296/0N
9.29 km
CreekPkg-1
306/1
9.68 km
MauvanaPkg-1
316/2
10.07 km
MauvanaPkg-1
326/3
10.49 km
MauvanaPkg-1
336/4
10.87 km
MauvanaPkg-1
346/5
11.20 km
MauvanaPkg-1
356/6
11.64 km
MauvanaPkg-1
366/7
12.03 km
MauvanaPkg-1
377/0
12.42 km
MauvanaPkg-1
387/1
12.76 km
MauvanaPkg-1
397/2
13.10 km
MauvanaPkg-1
407/3
13.50 km
MauvanaPkg-1
417/4
13.87 km
MauvanaPkg-1
427/5
14.27 km
MauvanaPkg-1
438/0
14.67 km
MauvanaPkg-1
449/0
14.90 km
MauvanaPkg-1
459/1
15.29 km
MauvanaPkg-1
469/2
15.66 km
MauvanaPkg-1
479/3
16.01 km
MauvanaPkg-1
489/4
16.49 km
MauvanaPkg-1
499/5
16.83 km
MauvanaPkg-1
509/6
17.32 km
MauvanaPkg-1
Page 1 of 5 · showing 50 of 232 filtered Bulk-set the 232 filtered rows:
Crossings & statutory approvals 3
S NoTypeSection AuthorityCurrent stagePending with Target dateRiskRemarks
22 220 / 132 / 66 kV lineAAI
23 220 / 132 / 66 kV lineAAI
24 220 / 132 / 66 kV lineCEA
Stringing sections 2
PackageFromTo kmStatus% doneT&C status
Pkg-11/018/0 39.5
Pkg-218/171/0 40.9
Dashboard Actions
data update, entry, editing and downloads
Save your work
Bring data in
Templates
Local copy
Audit Trail
every upload and manual change in this session
No changes yet. Upload a workbook or switch on Edit mode to start recording an audit trail.
How updating works

Weekly refresh. Click Update data (or drag the workbook anywhere onto this page) and pick the latest ROW Tracker.xlsx. The file is read in your browser — nothing is uploaded anywhere. A validation report appears first; you choose whether to load.

What comes from the Excel. RoW status and sub-issue, foundation / erection state, ageing, notice and meeting dates, remarks, crossings, and the statutory approval pipeline.

What stays fixed. Survey geometry — chainage, coordinates, tower type, deviation angle — is held as a baseline and is not overwritten, because it rarely changes and the tracker only carries it for some locations. New location numbers not in the baseline are placed by interpolation and flagged.

Sheet requirements. A sheet named Location Wise Details containing a header row with Tower Location No., plus columns Category, Village, EPC, Route Options, ROW Status, ROW sub-issue. Rows with Category = Tower and Route Options = RC form the corridor. A Statutory sheet refreshes crossings. Renaming a tab or a header is the one thing that will break it.

Manual edits. Edit mode lets you change status on any location and bulk-update selected rows. Edits live in this browser session only — they are never written back to your Excel automatically. Use Export Excel to produce a workbook (with a full audit sheet) to merge into the master tracker.

Ask
Answers are computed from the data loaded in this dashboard — figures always match the KPIs.
Drop the ROW Tracker workbook here
.xlsx · read locally in your browser · nothing is uploaded
Ready to load